Which account assignment category is important for non-valuated project stock with WBS and sales order item? Please choose the correct answer. Response:

The correct answer is A. D = quantities managed using sales order item and values managed in projects. See the full explanation below for the reasoning.

Question

Which account assignment category is important for non-valuated project stock with WBS and sales order item? Please choose the correct answer. Response:

Options

  • AD = quantities managed using sales order item and values managed in projects
  • BE = quantities and values managed in the sales order item
  • CG = plant stock, values managed using projects
  • DQ = quantities and values managed in projects

How the community answered

(26 responses)
  • A
    77% (20)
  • B
    8% (2)
  • C
    4% (1)
  • D
    12% (3)