C_TPLM22_67 · Question #155

Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer…

The correct answer is B. Network. See the full explanation below for the reasoning.

Question

Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM? Please choose the correct answer. Response:

Options

  • AMaterial view
  • BNetwork
  • CCost object
  • DAssignments

How the community answered

(55 responses)
  • A
    9% (5)
  • B
    73% (40)
  • C
    13% (7)
  • D
    5% (3)

Community Discussion

No community discussion yet for this question.