C_TPLM22_67 · Question #154

Which of the following can be derived automatically when you carry out scheduling in projects with networks? There are 2 correct answers to this question. Response:

The correct answer is C. Activity dates D. WBS element dates. See the full explanation below for the reasoning.

Question

Which of the following can be derived automatically when you carry out scheduling in projects with networks? There are 2 correct answers to this question. Response:

Options

  • AScheduling dates
  • BNetwork dates
  • CActivity dates
  • DWBS element dates

How the community answered

(33 responses)
  • A
    18% (6)
  • B
    9% (3)
  • C
    73% (24)

Community Discussion

No community discussion yet for this question.