SAP
C_TPLM22_67 · Question #130
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element. Which of the following costs can be planned?…
The correct answer is A. Each material B. Each internal activity D. Cost element level. See the full explanation below for the reasoning.
Question
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element. Which of the following costs can be planned? There are 3 correct answers to this question. Response:
Options
- AEach material
- BEach internal activity
- CInternal service
- DCost element level
How the community answered
(31 responses)- A71% (22)
- C29% (9)
Community Discussion
No community discussion yet for this question.