In which type of project stock costs from external procurement are posted directly to the stock-keeping WBS element when the goods or invoice are received? Please choose the correct answer. Response:

The correct answer is C. Non-valuated project stock. See the full explanation below for the reasoning.

Question

In which type of project stock costs from external procurement are posted directly to the stock-keeping WBS element when the goods or invoice are received? Please choose the correct answer. Response:

Options

  • ASales order project stock
  • BValuated project stock
  • CNon-valuated project stock
  • DNo project stock

How the community answered

(14 responses)
  • A
    7% (1)
  • B
    7% (1)
  • C
    86% (12)