C_TPLM22_67 · Question #1123
Which of the following information regarding cost activity is not relevant for the calculation of planned costs? Please choose the correct answer. Response:
The correct answer is A. Cost activities based on external services. See the full explanation below for the reasoning.
Question
Which of the following information regarding cost activity is not relevant for the calculation of planned costs? Please choose the correct answer. Response:
Options
- ACost activities based on external services
- BA unit costing that enables detailed planning with multiple cost elements, or an invoicing plan
- CThe cost element is defaulted for cost activities based on the network profile
- DControl key
How the community answered
(36 responses)- A78% (28)
- B3% (1)
- C6% (2)
- D14% (5)