To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element? There are 2 correct answers to this question. Response:
The correct answer is A. Account assignment element B. Billing element. See the full explanation below for the reasoning.
Question
To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element? There are 2 correct answers to this question. Response:
Options
- AAccount assignment element
- BBilling element
- CCost element
- DPricing element
How the community answered
(18 responses)- A78% (14)
- C17% (3)
- D6% (1)