C_TPLM22_67 · Question #112

Which of the following items can be included in the planned costs for an activity besides the cost of the activity? There are 3 correct answers to this question. Response:

The correct answer is A. Overheads determined through overhead costing sheet B. Activity elements C. Process costs determined through a process template. See the full explanation below for the reasoning.

Question

Which of the following items can be included in the planned costs for an activity besides the cost of the activity? There are 3 correct answers to this question. Response:

Options

  • AOverheads determined through overhead costing sheet
  • BActivity elements
  • CProcess costs determined through a process template
  • DMaterial management cost

How the community answered

(43 responses)
  • A
    79% (34)
  • D
    21% (9)

Community Discussion

No community discussion yet for this question.