nerdexam
SAP

C_TPLM22_67 · Question #111

Which indicator automates the grouping of project stock assigned to individual WBS elements to the top WBS element? Please choose the correct answer. Response:

The correct answer is C. Automatic requirement grouping. See the full explanation below for the reasoning.

Question

Which indicator automates the grouping of project stock assigned to individual WBS elements to the top WBS element? Please choose the correct answer. Response:

Options

  • AProject element indicator
  • BRequirements indicator
  • CAutomatic requirement grouping
  • DProject stock indicator

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    79% (23)
  • D
    10% (3)

Community Discussion

No community discussion yet for this question.

Full C_TPLM22_67 Practice