nerdexam
SAP

C_TFIN22_65 · Question #63

How do you receive the internal activities in the material cost estimate using a logistic quantity structure?

The correct answer is B. Assign a cost center and its activities in the work center of the routing operation. In material costing with a logistic quantity structure, internal activities are integrated by assigning a cost center and its activities to the work center used in a routing operation.

Product Cost Planning

Question

How do you receive the internal activities in the material cost estimate using a logistic quantity structure?

Options

  • AAssign the responsible cost center and its activities directly to the routing header.
  • BAssign a cost center and its activities in the work center of the routing operation.
  • CAssign a cost element with type 43 (internal activity allocation) to the routing operation.
  • DAssign a cost center and its activities to the bill of material.

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    89% (32)
  • C
    3% (1)
  • D
    3% (1)

Why each option

In material costing with a logistic quantity structure, internal activities are integrated by assigning a cost center and its activities to the work center used in a routing operation.

AAssign the responsible cost center and its activities directly to the routing header.

Assigning to the routing header is too general and does not specify which activities apply to which specific operation; activities are generally consumed at the operation level.

BAssign a cost center and its activities in the work center of the routing operation.Correct

In SAP, internal activities (like labor or machine time) are costed by linking them to work centers, which are then assigned to operations within a routing. The work center specifies the responsible cost center and the activity types performed, allowing the system to calculate the cost of these activities in the material cost estimate based on activity rates.

CAssign a cost element with type 43 (internal activity allocation) to the routing operation.

While cost element type 43 is for internal activity allocation, the mechanism for receiving these activities in the material cost estimate through a logistic quantity structure is via the work center and its assignment in the routing operation, not directly assigning the cost element to the operation.

DAssign a cost center and its activities to the bill of material.

A bill of material (BOM) specifies the raw materials and components, not internal activities; activities are defined in routings.

Concept tested: SAP Material Costing Internal Activities Integration

Source: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f3769910a30b4278ad0768b7501a3013/0c897f52f36f4d3de10000000a441753.html

Topics

#Internal activity allocation#Material cost estimate#Work center#Routings

Community Discussion

No community discussion yet for this question.

Full C_TFIN22_65 Practice