C_TFIN22_65 · Question #42

Which data can be saved when storing a material cost estimate with quantity structure? Note: There are 3 correct answers to this question.

The correct answer is A. Log B. Cost components split D. Itemization. When storing a material cost estimate with quantity structure, the system saves the calculation log, the detailed cost components split, and the itemization of all cost elements and quantities.

Product Cost Planning

Question

Which data can be saved when storing a material cost estimate with quantity structure? Note:

There are 3 correct answers to this question.

Options

  • ALog
  • BCost components split
  • CExtract
  • DItemization
  • EVariance categories

How the community answered

(30 responses)
  • A
    93% (28)
  • C
    3% (1)
  • E
    3% (1)

Why each option

When storing a material cost estimate with quantity structure, the system saves the calculation log, the detailed cost components split, and the itemization of all cost elements and quantities.

ALogCorrect

The log records all messages, warnings, and errors that occurred during the costing run, providing an audit trail and troubleshooting information for the cost estimate.

BCost components splitCorrect

The cost components split breaks down the total cost into user-defined categories (e.g., material costs, labor costs, overheads), providing a structured view of the cost composition.

CExtract

An 'extract' is not a standard saved data component of a material cost estimate in the SAP system in this context; rather, the itemization and cost component split are the detailed data.

DItemizationCorrect

The itemization provides a detailed list of all individual cost elements, quantities, and prices that make up the cost estimate, showing the calculation's granular steps.

EVariance categories

Variance categories are typically associated with actual cost analysis (e.g., production order variances) after a period of activity, not directly saved as part of a standard material cost estimate's initial storage.

Concept tested: Data saved in material cost estimates

Source: https://help.sap.com/doc/saphelp_erp600_ehp07/latest/en-US/a5/d28653ee2b7e5fe10000000a174bc4/frameset.htm

Topics

#material cost estimate#quantity structure#cost components split#itemization