A customer wants to perform cost center planning to reflect different expectations for the future. How can the customer create different plans in parallel?

The correct answer is A. Use different versions. See the full explanation below for the reasoning.

Question

A customer wants to perform cost center planning to reflect different expectations for the future. How can the customer create different plans in parallel?

Options

  • AUse different versions.
  • BUse different costing variants.
  • CUse different planning areas.
  • DUse different valuation areas.

How the community answered

(35 responses)
  • A
    80% (28)
  • B
    11% (4)
  • C
    3% (1)
  • D
    6% (2)