C_TFIN22_64 · Question #68
Which planning transactions create secondary costs on the receivers? Note: There are 2 correct answers to this question.
The correct answer is A. Plan assessment E. Activity input planning. See the full explanation below for the reasoning.
Question
Which planning transactions create secondary costs on the receivers? Note: There are 2 correct answers to this question.
Options
- APlan assessment
- BTransfer of depreciations from Asset Accounting
- CTransfer of personnel cost from HR
- DPlan distribution
- EActivity input planning
How the community answered
(29 responses)- A83% (24)
- B3% (1)
- C10% (3)
- D3% (1)
Community Discussion