The Operative Indicator, Account Assignment Element is used when you want to plan costs for WBS elements. Please choose the correct answer.

The correct answer is B. False. See the full explanation below for the reasoning.

Question

The Operative Indicator, Account Assignment Element is used when you want to plan costs for WBS elements. Please choose the correct answer.

Options

  • ATrue
  • BFalse

How the community answered

(25 responses)
  • A
    20% (5)
  • B
    80% (20)