nerdexam
SAP

C_TERP10_67 · Question #165

Which period-end closing activity for manufacturing orders integrates with management accounting?

The correct answer is C. Variance calculation. See the full explanation below for the reasoning.

Question

Which period-end closing activity for manufacturing orders integrates with management accounting?

Options

  • AOrder confirmation
  • BInternal activity allocation
  • CVariance calculation
  • DGoods issue

How the community answered

(52 responses)
  • A
    6% (3)
  • B
    17% (9)
  • C
    69% (36)
  • D
    8% (4)

Community Discussion

No community discussion yet for this question.

Full C_TERP10_67 Practice