C_TERP10_67 · Question #72

Within a MRP net requirements calculation, which of the following are demand elements? Note: There are 3 correct answers to this question.

The correct answer is C. Planned independent requirements E. Safety stock. See the full explanation below for the reasoning.

Question

Within a MRP net requirements calculation, which of the following are demand elements? Note: There are 3 correct answers to this question.

Options

  • APurchase order
  • BOn hand inventory
  • CPlanned independent requirements
  • DSales order
  • ESafety stock

How the community answered

(13 responses)
  • B
    15% (2)
  • C
    77% (10)
  • D
    8% (1)