SAP
C_TERP10_67 · Question #22
In Logistics Execution, which of the following are true? There are 2 correct answers to this question.
The correct answer is B. Shipping points can be assigned to more than one plant D. Transportation planning points are necessary for cost calculation. See the full explanation below for the reasoning.
Question
In Logistics Execution, which of the following are true? There are 2 correct answers to this question.
Options
- AWarehouse numbers are assigned to only one plant
- BShipping points can be assigned to more than one plant
- CTransportation planning points can be assigned to one or more plants
- DTransportation planning points are necessary for cost calculation
How the community answered
(25 responses)- A8% (2)
- B72% (18)
- C20% (5)
Community Discussion
No community discussion yet for this question.