Your organization creates purchase orders for consumable materials and has activated commitments management. What is created when a purchase order for consumable materials is saved?

The correct answer is A. A commitment in Controlling (CO). See the full explanation below for the reasoning.

Question

Your organization creates purchase orders for consumable materials and has activated commitments management. What is created when a purchase order for consumable materials is saved?

Options

  • AA commitment in Controlling (CO)
  • BA financial accounting document
  • CA commitment in Financial Accounting (FI)
  • DA requirement coverage in material requirements planning

How the community answered

(31 responses)
  • A
    81% (25)
  • B
    3% (1)
  • C
    3% (1)
  • D
    13% (4)