C_TERP10_67 · Question #180

In Project System, what represents a model of a project and includes assigned project activities in hierarchical form?

The correct answer is B. Work breakdown structure. See the full explanation below for the reasoning.

Question

In Project System, what represents a model of a project and includes assigned project activities in hierarchical form?

Options

  • AActivities
  • BWork breakdown structure
  • CProject definition
  • DNetwork

How the community answered

(69 responses)
  • A
    4% (3)
  • B
    78% (54)
  • C
    3% (2)
  • D
    14% (10)