C_TERP10_67 · Question #178
You have assigned a budget to WBS elements within your project. Which function can you use to ensure that the system automatically checks for a budget overrun?
The correct answer is D. Availability control. See the full explanation below for the reasoning.
Question
You have assigned a budget to WBS elements within your project. Which function can you use to ensure that the system automatically checks for a budget overrun?
Options
- AResults analysis
- BProject settlement
- CCost forecast
- DAvailability control