SAP
C_TERP10_67 · Question #170
You are setting the control parameters in the initial screen for material requirements planning (MRP). Which control parameter defines the planning type as regenerative or net change planning?
The correct answer is B. Processing key. See the full explanation below for the reasoning.
Question
You are setting the control parameters in the initial screen for material requirements planning (MRP). Which control parameter defines the planning type as regenerative or net change planning?
Options
- AOpening period
- BProcessing key
- CLot size key
- DMRP group
How the community answered
(19 responses)- A16% (3)
- B74% (14)
- C5% (1)
- D5% (1)
Community Discussion
No community discussion yet for this question.