SAP
C_TERP10_67 · Question #112
Three different cost planning levels are available for planning internal order what are they? There are 2 correct answers to this question.
The correct answer is B. Overall planning C. Primary/secondary cost and revenue planning D. Unit costing. See the full explanation below for the reasoning.
Question
Three different cost planning levels are available for planning internal order what are they? There are 2 correct answers to this question.
Options
- AIndustrial planning
- BOverall planning
- CPrimary/secondary cost and revenue planning
- DUnit costing
- ECost Budgeting
How the community answered
(28 responses)- A14% (4)
- B75% (21)
- E11% (3)
Community Discussion