Three different cost planning levels are available for planning internal order what are they? There are 2 correct answers to this question.

The correct answer is B. Overall planning C. Primary/secondary cost and revenue planning D. Unit costing. See the full explanation below for the reasoning.

Question

Three different cost planning levels are available for planning internal order what are they? There are 2 correct answers to this question.

Options

  • AIndustrial planning
  • BOverall planning
  • CPrimary/secondary cost and revenue planning
  • DUnit costing
  • ECost Budgeting

How the community answered

(28 responses)
  • A
    14% (4)
  • B
    75% (21)
  • E
    11% (3)