C_TERP10_67 · Question #110
You are explaining SAP ERP Material Planning to your colleagues. They are interested in learning about the functions of material requirements planning (MRP). Which of the following statements…
The correct answer is A. MRP can be run at the plant level. D. The suggested procurement quantity results from the lot-sizing procedure that is set inthe. See the full explanation below for the reasoning.
Question
You are explaining SAP ERP Material Planning to your colleagues. They are interested in learning about the functions of material requirements planning (MRP). Which of the following statements correctly describe the features of MRP? There are 2 correct answers to this question.
Options
- AMRP can be run at the plant level.
- BMRP will first use forward scheduling to calculate the requirement's date.
- CRegenerative MRP planning will plan only those materials that have been subjected toan MRP
- DThe suggested procurement quantity results from the lot-sizing procedure that is set inthe
How the community answered
(33 responses)- A70% (23)
- B18% (6)
- C12% (4)