C_TERP10_66 · Question #94

In production execution, the availability check, checks for which of the following? (Choose all that apply)

The correct answer is A. Components B. Capacities C. PRT s. See the full explanation below for the reasoning.

Question

In production execution, the availability check, checks for which of the following? (Choose all that apply)

Options

  • AComponents
  • BCapacities
  • CPRT s
  • DBOM s

How the community answered

(55 responses)
  • A
    75% (41)
  • D
    25% (14)