Consumption based planning can be done on the following levels (Choose all that apply)
The correct answer is A. Reorder-point planning C. Forecast-based planning D. Time-phased planning. See the full explanation below for the reasoning.
Question
Consumption based planning can be done on the following levels (Choose all that apply)
Options
- AReorder-point planning
- BBased on independent requirements
- CForecast-based planning
- DTime-phased planning
How the community answered
(45 responses)- A73% (33)
- B27% (12)