Time periods in the standard planning table could be (Choose all that apply)

The correct answer is B. Days C. Weeks D. Accounting periods E. Sales periods. See the full explanation below for the reasoning.

Question

Time periods in the standard planning table could be (Choose all that apply)

Options

  • AMinutes
  • BDays
  • CWeeks
  • DAccounting periods
  • ESales periods

How the community answered

(28 responses)
  • A
    18% (5)
  • B
    82% (23)

Community Discussion