A standard cost estimate is created in product cost planning. Which of the following is correct?
The correct answer is B. Releasing a standard cost estimate revaluates on-hand inventory. See the full explanation below for the reasoning.
Question
A standard cost estimate is created in product cost planning. Which of the following is correct?
Options
- AThe quantity structure is used to calculate material overhead.
- BReleasing a standard cost estimate revaluates on-hand inventory.
- CThe actual production costs are rolled up.
- DSaving a standard cost estimate automatically updates the standard price field in the material
How the community answered
(32 responses)- A3% (1)
- B78% (25)
- C6% (2)
- D13% (4)