SAP
C_TERP10_66 · Question #40
Your organization creates purchase orders for consumable materials and has activated commitments management. What is created when a purchase order for consumable materials is saved?
The correct answer is A. A commitment in Controlling (CO). See the full explanation below for the reasoning.
Question
Your organization creates purchase orders for consumable materials and has activated commitments management. What is created when a purchase order for consumable materials is saved?
Options
- AA commitment in Controlling (CO)
- BA financial accounting document
- CA commitment in Financial Accounting (FI)
- DA requirement coverage in material requirements planning
How the community answered
(30 responses)- A70% (21)
- B7% (2)
- C7% (2)
- D17% (5)
Community Discussion
No community discussion yet for this question.