Your organization creates purchase orders for consumable materials and has activated commitments management. What is created when a purchase order for consumable materials is saved?

The correct answer is A. A commitment in Controlling (CO). See the full explanation below for the reasoning.

Question

Your organization creates purchase orders for consumable materials and has activated commitments management. What is created when a purchase order for consumable materials is saved?

Options

  • AA commitment in Controlling (CO)
  • BA financial accounting document
  • CA commitment in Financial Accounting (FI)
  • DA requirement coverage in material requirements planning

How the community answered

(30 responses)
  • A
    70% (21)
  • B
    7% (2)
  • C
    7% (2)
  • D
    17% (5)