C_TERP10_66 · Question #32
You have assigned a budget to WBS elements within your project. Which function can you use to ensure that the system automatically checks for a budget overrun?
The correct answer is D. Availability control. See the full explanation below for the reasoning.
Question
You have assigned a budget to WBS elements within your project. Which function can you use to ensure that the system automatically checks for a budget overrun?
Options
- AResults analysis
- BProject settlement
- CCost forecast
- DAvailability control
How the community answered
(36 responses)- A8% (3)
- B17% (6)
- C6% (2)
- D69% (25)