C_TERP10_66 · Question #169

In Project System, which of the following operative indicators can you set in a WBS element? Note: There are three (3) correct answers to this question.

The correct answer is A. Planning element B. Billing element E. Account assignment element. See the full explanation below for the reasoning.

Question

In Project System, which of the following operative indicators can you set in a WBS element? Note: There are three (3) correct answers to this question.

Options

  • APlanning element
  • BBilling element
  • CBudgeting element
  • DCost element
  • EAccount assignment element

How the community answered

(26 responses)
  • A
    81% (21)
  • C
    8% (2)
  • D
    12% (3)