C_TERP10_66 · Question #166

Which of the following statements regarding bills of material (BOM) in the material planning business process are correct? Note: There are two (2) correct answers to this question?

The correct answer is B. The quantities in the line items refer to the base quantity defined in the BOM header. C. BOM usage determines the business applications for which a BOM can be used. See the full explanation below for the reasoning.

Question

Which of the following statements regarding bills of material (BOM) in the material planning business process are correct? Note: There are two (2) correct answers to this question?

Options

  • AAll components listed in the BOM line items require a material master record.
  • BThe quantities in the line items refer to the base quantity defined in the BOM header.
  • CBOM usage determines the business applications for which a BOM can be used.
  • DBOMs are created and maintained as multilevel bills.

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    84% (27)
  • D
    6% (2)

Community Discussion

No community discussion yet for this question.