Which of the following fields are required to create a cost Canter in management accounting (CO)? Note: There are two (2) correct answers to this question.
The correct answer is C. Hierarchy area D. Company code. See the full explanation below for the reasoning.
Question
Which of the following fields are required to create a cost Canter in management accounting (CO)? Note: There are two (2) correct answers to this question.
Options
- AUser responsible
- BDescription
- CHierarchy area
- DCompany code
How the community answered
(18 responses)- A6% (1)
- B11% (2)
- C83% (15)