C_TERP10_66 · Question #140
C_TERP10_66 Question #140: Real Exam Question with Answer & Explanation
The correct answer is B. Confirmation. See the full explanation below for the reasoning.
Question
Your organization uses SAP ERP Manufacturing Execution. You are reviewing a production order and notice that no labor time has been recorded in the production order. Which Manufacturing Execution business process step has not been completed?
Options
- AGoods issue
- BConfirmation
- CGoods receipt
- DOrder settlement
- EVariance calculation