The correct answer is B. Confirmation. See the full explanation below for the reasoning.

Question

Your organization uses SAP ERP Manufacturing Execution. You are reviewing a production order and notice that no labor time has been recorded in the production order. Which Manufacturing Execution business process step has not been completed?

Options

  • AGoods issue
  • BConfirmation
  • CGoods receipt
  • DOrder settlement
  • EVariance calculation