In PM, you can display expected costs in which ways? (Choose all that apply)
The correct answer is B. Cost element level C. Value category level. See the full explanation below for the reasoning.
Question
In PM, you can display expected costs in which ways? (Choose all that apply)
Options
- AOperation level
- BCost element level
- CValue category level
- DBOM level
How the community answered
(38 responses)- A5% (2)
- B84% (32)
- D11% (4)