Consumption based planning can be done on the following levels (Choose all thatapply)

The correct answer is A. Reorder-point planning C. Forecast-based planning D. Time-phased planning. See the full explanation below for the reasoning.

Question

Consumption based planning can be done on the following levels (Choose all thatapply)

Options

  • AReorder-point planning
  • BBased on independent requirements
  • CForecast-based planning
  • DTime-phased planning

How the community answered

(46 responses)
  • A
    80% (37)
  • B
    20% (9)

Community Discussion