C_TERP10_60 · Question #86
The Kanban production type does not run with MRP. (True/False)
The correct answer is A. True. See the full explanation below for the reasoning.
Question
The Kanban production type does not run with MRP. (True/False)
Options
- ATrue
- BFalse
How the community answered
(59 responses)- A76% (45)
- B24% (14)