Your organization is implementing SAP ERP Logistics Execution. As a project team member, you are responsible for defining and assigning the organizational levels relevant for Logistics Execution.How…

The correct answer is B. Several plant-storage location combinations can be assigned to one warehouse number. See the full explanation below for the reasoning.

Question

Your organization is implementing SAP ERP Logistics Execution. As a project team member, you are responsible for defining and assigning the organizational levels relevant for Logistics Execution.How would you correctly assign the organizational levels?

Options

  • AA transportation planning point can be assigned to a plant.
  • BSeveral plant-storage location combinations can be assigned to one warehouse number.
  • CA plant-storage location combination can be assigned to multiple warehouse numbers.
  • DA plant-storage location and storage area combination can be assigned to one warehouse
  • EA plant-storage location combination can be assigned to several shipping points.

How the community answered

(25 responses)
  • A
    16% (4)
  • B
    72% (18)
  • D
    8% (2)
  • E
    4% (1)