Your organization is implementing SAP ERP Logistics Execution. As a project team member, you are responsible for defining and assigning the organizational levels relevant for Logistics Execution.How…
The correct answer is B. Several plant-storage location combinations can be assigned to one warehouse number. See the full explanation below for the reasoning.
Question
Your organization is implementing SAP ERP Logistics Execution. As a project team member, you are responsible for defining and assigning the organizational levels relevant for Logistics Execution.How would you correctly assign the organizational levels?
Options
- AA transportation planning point can be assigned to a plant.
- BSeveral plant-storage location combinations can be assigned to one warehouse number.
- CA plant-storage location combination can be assigned to multiple warehouse numbers.
- DA plant-storage location and storage area combination can be assigned to one warehouse
- EA plant-storage location combination can be assigned to several shipping points.
How the community answered
(25 responses)- A16% (4)
- B72% (18)
- D8% (2)
- E4% (1)