nerdexam
SAP

C_TERP10_60 · Question #5

Consumption based planning can be done on the following levels (Choose all thatapply)

The correct answer is A. Reorder-point planning C. Forecast-based planning D. Time-phased planning. See the full explanation below for the reasoning.

Question

Consumption based planning can be done on the following levels (Choose all thatapply)

Options

  • AReorder-point planning
  • BBased on independent requirements
  • CForecast-based planning
  • DTime-phased planning

How the community answered

(32 responses)
  • A
    75% (24)
  • B
    25% (8)

Community Discussion

No community discussion yet for this question.

Full C_TERP10_60 Practice