C_TERP10_60 · Question #5
Consumption based planning can be done on the following levels (Choose all thatapply)
The correct answer is A. Reorder-point planning C. Forecast-based planning D. Time-phased planning. See the full explanation below for the reasoning.
Question
Consumption based planning can be done on the following levels (Choose all thatapply)
Options
- AReorder-point planning
- BBased on independent requirements
- CForecast-based planning
- DTime-phased planning
How the community answered
(32 responses)- A75% (24)
- B25% (8)