Murielle, from Noah industries, issued a purchase order for 100 inventory items. The vendor delivered only 75 items, and promises to deliver the remainder in two or three weeks. Murielle wants to…

The correct answer is B. Create a goods receipt PO based on the original purchase order, and modify the quantity. See the full explanation below for the reasoning.

Question

Murielle, from Noah industries, issued a purchase order for 100 inventory items. The vendor delivered only 75 items, and promises to deliver the remainder in two or three weeks. Murielle wants to generate a goods receipt PO to reflect the receipt of the items in stock, but does not know how to enter a partial delivery in the system. What is the best way to do this?

Options

  • ACreate a goods receipt PO based on the original purchase order, and copy the entire quantity.
  • BCreate a goods receipt PO based on the original purchase order, and modify the quantity
  • CCreate a goods receipt PO for the actual quantity delivered, and save it as a draft.
  • DReduce the amount on the original purchase order to match the delivered amount before

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    77% (17)
  • C
    5% (1)
  • D
    14% (3)