C_TB1200_10 · Question #7
In routed production order stages, which stage element can be affected by the routing date calculation field value?
The correct answer is A. Start date. Option A is correct because the routing date calculation field directly controls how the system computes when each stage in a routed production order should begin - it determines the start date for individual routing operations by working forward or backward from the production…
Question
In routed production order stages, which stage element can be affected by the routing date calculation field value?
Options
- AStart date
- BWaiting days
- CStatus
- DRun time
How the community answered
(15 responses)- A80% (12)
- B7% (1)
- D13% (2)
Explanation
Option A is correct because the routing date calculation field directly controls how the system computes when each stage in a routed production order should begin - it determines the start date for individual routing operations by working forward or backward from the production order's target date.
Why the distractors are wrong:
- B (Waiting days): Waiting days are a fixed, manually entered value on the routing line or work center; they are an input to scheduling, not an output of the date calculation field.
- C (Status): Status reflects the processing state of the order (e.g., Planned, Released, Finished) and is driven by user actions or order posting, not by date calculation logic.
- D (Run time): Run time is determined by work center capacity and the operation's setup, and remains constant regardless of how dates are calculated.
Memory tip: Associate "routing date calculation" with the one thing that is always a date - the Start date. If you're calculating dates, you're setting when something starts, not changing how long it runs or what its status is.