SAP
C_TADM70_73 · Question #98
An SAP implementation project must change the database system before going into production, because of strategic customer decisions. The customer system configuration was setup as a standard…
The correct answer is A. It is not necessary. See the full explanation below for the reasoning.
Question
An SAP implementation project must change the database system before going into production, because of strategic customer decisions. The customer system configuration was setup as a standard three-system landscape (development, quality assurance, production). Each system is configured as ABAP Web AS with JAVA Add-in. Is it necessary to order a SAP OS/DB Migration Check for the planned database change?
Options
- AIt is not necessary
- BIt is necessary
How the community answered
(14 responses)- A71% (10)
- B29% (4)
Community Discussion