As SAP implementation project must change the database system before into production because of strategic customer decision. The customer system configuration was setup as a standard three-system…
The correct answer is A. It is not necessary. See the full explanation below for the reasoning.
Question
As SAP implementation project must change the database system before into production because of strategic customer decision. The customer system configuration was setup as a standard three-system landscape(development, quality assurance, production). Each system is configured as ABAP Web AS with JAVA Add-in
Options
- AIt is not necessary
- BIt is necessary
How the community answered
(30 responses)- A83% (25)
- B17% (5)