A customer SAP system landscaped is made up of several systems. All system have to be migrated to a different database. System set 1 (ERP): Development, Quality Assurance, Production. System set 2…

The correct answer is A. 1 X Development, 2 x Production, Homogeneous system copy from production to Quality C. 1 X Development, 1 X Quality Assurance, 2 X production. See the full explanation below for the reasoning.

Question

A customer SAP system landscaped is made up of several systems. All system have to be migrated to a different database. System set 1 (ERP): Development, Quality Assurance, Production. System set 2 (BW): Development, Production. How many system copies are involved for syatem set 1(ERP)?

Options

  • A1 X Development, 2 x Production, Homogeneous system copy from production to Quality
  • B1 x Development, 2 X production
  • C1 X Development, 1 X Quality Assurance, 2 X production.
  • D2 X Development, 2 X Production.

How the community answered

(23 responses)
  • A
    83% (19)
  • B
    13% (3)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.