C_TADM70_73 · Question #51
A customer SAP system landscape is made up of several systems, all systems have to be migrated to a different database. System set 1 (ERP): Development, Quality Assurance, Production System set 2…
The correct answer is C. 1 X Development, 2 X Production. See the full explanation below for the reasoning.
Question
A customer SAP system landscape is made up of several systems, all systems have to be migrated to a different database. System set 1 (ERP): Development, Quality Assurance, Production System set 2 (BW):
Development, Production. How may system copies are involved for system 2 (BW)?
Options
- A2 X Development, 2 X Production.
- B1 X Development, 1 X Quality Assurance, 2 X Production
- C1 X Development, 2 X Production
- D1 X Development, 2 X Production, homogeneous system copy from production to Quality
How the community answered
(46 responses)- A9% (4)
- B7% (3)
- C80% (37)
- D4% (2)