SAP
C_S4TM_2023 · Question #15
The following settings are defined for a freight order from location A to location B with two freight units: - The distance between locations A and B in the transportation lane is 1500 km, the…
The correct answer is B. Tuesday 7:30 am. Explanation/Reference:
Transportation Planning
Question
The following settings are defined for a freight order from location A to location B with two freight units:
- The distance between locations A and B in the transportation lane is 1500 km, the duration is 19
hours, and the Fix Transportation Duration flag is set.
- The average speed for the means of transport is defined as 100 km/h and the GIS quality flag is
NOT set.
- Loading and unloading of each freight unit at locations A and B is defined as 1 hour. The vehicle
resource is available weekdays from 8:00 am to 8:00 pm.
- Loading starts on Monday at 8:30 am.
When is unloading finished?
Options
- ATuesday 6:30 pm
- BTuesday 7:30 am
- CTuesday 7:30 pm
- DTuesday 5:30 pm
How the community answered
(38 responses)- A5% (2)
- B66% (25)
- C18% (7)
- D11% (4)
Explanation
Explanation/Reference:
Topics
#scheduling#fixed transportation duration#vehicle resource availability#time calculation