The following settings are defined for a freight order from location A to location B with two freight units: - The distance between locations A and B in the transportation lane is 1500 km, the…

The correct answer is B. Tuesday 7:30 am. Explanation/Reference:

Transportation Planning

Question

The following settings are defined for a freight order from location A to location B with two freight units:

  • The distance between locations A and B in the transportation lane is 1500 km, the duration is 19

hours, and the Fix Transportation Duration flag is set.

  • The average speed for the means of transport is defined as 100 km/h and the GIS quality flag is

NOT set.

  • Loading and unloading of each freight unit at locations A and B is defined as 1 hour. The vehicle

resource is available weekdays from 8:00 am to 8:00 pm.

  • Loading starts on Monday at 8:30 am.

When is unloading finished?

Options

  • ATuesday 6:30 pm
  • BTuesday 7:30 am
  • CTuesday 7:30 pm
  • DTuesday 5:30 pm

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    66% (25)
  • C
    18% (7)
  • D
    11% (4)

Explanation

Explanation/Reference:

Topics