C_S4EWM_2020 · Question #86
Your customer wants to use batch management in SAP Extended Warehouse Management (SAP EWM). When do you have to create a batch during the inbound process?
The correct answer is C. Before the inbound delivery is created in SAP ERP. In a decentralized SAP EWM setup, batch master data is managed in SAP ERP, not in EWM. The inbound delivery in ERP must reference a valid batch on its line items, which means the batch record must already exist before that delivery is created in ERP - making C the only correct…
Question
Your customer wants to use batch management in SAP Extended Warehouse Management (SAP EWM). When do you have to create a batch during the inbound process?
Options
- ABefore the goods receipt is posted in SAP EWM
- BBefore the inbound delivery is created in SAP EWM
- CBefore the inbound delivery is created in SAP ERP
- DBefore the inbound delivery is distributed from SAP ERP to SAP EWM
How the community answered
(35 responses)- A17% (6)
- B6% (2)
- C71% (25)
- D6% (2)
Explanation
In a decentralized SAP EWM setup, batch master data is managed in SAP ERP, not in EWM. The inbound delivery in ERP must reference a valid batch on its line items, which means the batch record must already exist before that delivery is created in ERP - making C the only correct timing.
Why the distractors are wrong:
- A (before goods receipt in EWM): Far too late - the delivery has already been created in ERP and distributed to EWM by this point; the system would have already failed to reference the batch.
- B (before inbound delivery is created in EWM): The EWM delivery is generated automatically when the ERP delivery is distributed, so this moment is already downstream of where the batch must exist.
- D (before distribution from ERP to EWM): Close, but still too late - the batch must exist when the ERP delivery is created, not merely before it is sent to EWM. By distribution time, the ERP delivery document is already finalized.
Memory tip: Think of the flow as a chain - Batch → ERP Delivery → Distribution → EWM Delivery → GR. The batch must be at the very beginning of that chain because every downstream step depends on it. "ERP delivery can't reference what doesn't exist yet."