Your customer requires each product to be stored in its own preassigned place in the warehouse. Which putaway strategy meets this requirement? Please choose the correct answer.

The correct answer is D. Fixed storage bin. You've hit your limit · resets 12:50am (America/New_York)

Inbound Processes

Question

Your customer requires each product to be stored in its own preassigned place in the warehouse. Which putaway strategy meets this requirement? Please choose the correct answer.

Options

  • AAddition to existing stock
  • BEmpty storage bin
  • CManual entry
  • DFixed storage bin

How the community answered

(36 responses)
  • B
    6% (2)
  • C
    3% (1)
  • D
    92% (33)

Explanation