How is the KPI contract leakage percentage defined?
The correct answer is C. Spend of purchase orders without contract reference despite existing contract. You've hit your limit · resets 12:50am (America/New_York)
Collaboration and Analytics
Question
How is the KPI contract leakage percentage defined?
Options
- AQuantity of purchase orders without contract reference despite existing contract
- BConfirmed quantity of purchase orders with contract reference
- CSpend of purchase orders without contract reference despite existing contract
- DConfirmed spend of purchase orders with contract reference
How the community answered
(19 responses)- A5% (1)
- C89% (17)
- D5% (1)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#KPI#contract leakage#spend management#procurement analytics