Which analytical list page do you use to display the difference between the net value and the committed quantity value?
The correct answer is C. Monitor Supplier Confirmations. You've hit your limit · resets 12:50am (America/New_York)
Collaboration and Analytics
Question
Which analytical list page do you use to display the difference between the net value and the committed quantity value?
Options
- AMonitor Purchase Order Items
- BMaterial Price Variance
- CMonitor Supplier Confirmations
- DMonitor Scheduling Agreement Items
How the community answered
(37 responses)- A3% (1)
- B3% (1)
- C86% (32)
- D8% (3)
Explanation
You've hit your limit · resets 12:50am (America/New_York)
Topics
#Monitor Supplier Confirmations#analytical list page#committed quantity#net value variance