In which phase of the project can a project manager create a billing proposal?
The correct answer is C. In the Contract Preparation phase. See the full explanation below for the reasoning.
Question
In which phase of the project can a project manager create a billing proposal?
Options
- AIn the Execution phase
- BIn the Fit to Standard Analysis phase
- CIn the Contract Preparation phase
- DIn the Planning phase
How the community answered
(36 responses)- A14% (5)
- B8% (3)
- C75% (27)
- D3% (1)